Dispatches from the MARK

Stay up to date on everything that’s happening, from upcoming events to project information.

PROJECT UPDATES - MAY 2015

Posted on

MAJOR ACTIVITIES

Shoring & Excavation
Shoring and tiebacks are nearing completion. Night haul trucking will continue as it reduces the impacts to the public and the environment. Tiebacks are scheduled for completion along with excavation in late April/early May 2015. 

PUBLIC IMPACTS

5th Avenue
For safety, the west sidewalk between Columbia Street and Marion Street will remain closed to pedestrians throughout the duration of the project. The west side traffic lane will be closed for construction Monday - Friday, between 6 p.m. and 3 p.m. and on Saturdays (9 a.m. to 6 p.m.) as required. 

Columbia St
The north sidewalk between 5th Avenue and 4th Avenue will remain closed throughout the duration of the project as this is an active truck haul route and will serve as the location for a construction elevator and other primary building functions. 

Mobilization/Street Closures
A second conveyor was mobilized on April 11th. Tower crane erection is scheduled for May 16th, 30th, and the 31st. The mat foundation pour is scheduled for June 20th. All of these activities will require major street closures. Individual traffic control and logistics plans will be sent out as the dates of these activities near. 

Recent Posts

Archives